Spokane passes 50 fire rebuild permits as plan reviews average two days

Spokane has issued 50 rebuild permits for homes lost in the Spokane Complex Fire, with reviews averaging two days. Here's what rebuild contractors should know.

Damage from the Old Trails Fire in the Spokane area. Photo: U.S. Forest Service via Wikimedia Commons, public domain

Fifty households that lost homes in this summer's Spokane Complex Fire now have permits to rebuild inside Spokane city limits, and the city says its reviewers are turning fire-related plan sets around in about two days (via City of Spokane). The city announced the milestone Nov. 24, almost four months after the Old Trails Fire crossed the Spokane River and burned into the Indian Trail and Westgate neighborhoods.

Here's where the numbers stand. On top of the 50 issued rebuild permits, another 18 units are in plan review. Initial reviews and revision reviews on fire-related permits are averaging two days, and the median time from submittal to acceptance is five days, according to the city. Staff at the Development Services Center (DSC) say they're pushing fire work through quickly while still meeting the pledge dates they give on routine permits.

Demolition is further along than rebuilding. The city has opened 326 demolition permits: 221 have been issued, 95 have been finaled and 10 are still in review. By the city's count, that means nearly 60 percent of damaged homes inside city limits have started the demolition permit process, which also means roughly four in ten haven't started yet.

There are two gates before any demolition permit gets issued: hazardous waste has to be cleared off the lot, and the structure needs an asbestos survey. The city says the U.S. Environmental Protection Agency has now finished hazardous-waste removal at every impacted home, so the asbestos survey is the step most owners still have to line up.

The city is covering that cost when insurance doesn't. Owners of properties hit by the Old Trails Fire, one of the fires in the Spokane Complex, can request a free survey through an online city form. Owners who already paid for an asbestos test that insurance didn't cover can use the same form to ask for retroactive payment of up to $1,600.

The rest of the sequence was laid out in the city's August guidance when it issued the first rebuild permit. If the survey comes back negative, the owner or a contractor can remove the debris. If it comes back positive, the work needs a Washington-certified asbestos abatement company. Either way, a Notice of Intent has to be filed with the Spokane Regional Clean Air Agency before the city will issue a demolition or building permit.

The city also cut its demolition permit fee to $35 for owners of wildfire-affected properties and waived the processing and technology fees. For homes built after Feb. 1, 2021, the DSC kept the electronic design plans on file, so owners can rebuild from previously approved plans or bring in new ones.

That first rebuild permit, issued Aug. 27, came two days after the application arrived on Aug. 25. The Old Trails Fire was one of three wildfires that started during an extreme heat and wind event in early August; OPB reported the fires burned more than 900 structures.

Mayor Lisa Brown tied the milestone to the families doing the rebuilding. "Behind each of these 50 permits is a survivor who has faced the difficult reality of losing a home and the long road toward rebuilding," Brown said in the release. She thanked the DSC team and said she hopes the milestone "serves as a reminder that recovery is happening, even when the process can feel slow."

Why it matters for Contractors

This is a steady pipeline of single-family rebuild work, the kind of job a small shop can take on. Fifty homes are permitted, 18 more are in review and 221 lots have demolition permits, so a lot of sites are heading toward foundations. With roughly 40 percent of damaged homes yet to start demolition, more of that work is still coming.

The fast review clock rewards clean submittals. When initial and revision reviews run about two days, a complete plan set moves quickly and every resubmittal is lost time. If your client's home was built after Feb. 1, 2021, ask whether its approved plans are already on file with the DSC before paying for new drawings.

Get the order right before you schedule a crew. Demolition waits on EPA clearance, an asbestos survey and a Clean Air Notice of Intent. Point clients whose insurance won't cover the survey to the city's free form, and to the $1,600 reimbursement if they already paid. If a survey comes back positive, that debris goes to a certified abatement company, not your crew, unless you hold that certification.

Questions on fire permits go to the DSC at PermitTeam@spokanecity.org or 509-625-6300.