A small workforce rental building planned for a long-empty city lot in Waikiki is one vote away from a lease. The Honolulu City Council's Zoning and Planning Committee voted 4-0 on Nov. 18 to advance Resolution 26-237, which would let the city sign a pre-development agreement and a 75-year ground lease for a project called Cardinal at Ala Wai at 1615 Ala Wai Blvd. (via City and County of Honolulu).
The committee passed an amended version, labeled CD1. The resolution now heads to the full council. If it's adopted there, the city says it'll execute the agreements needed to move the project forward. No date for that vote was given in the release.
The plan calls for a six-story building with about 40 one-bedroom apartments, an elevator and seven parking stalls on site, including accessible spaces. That's a modest count, but the lot is small: roughly 9,450 square feet, according to both the city's release and a public hearing notice published last summer.
Affordability is split into two tiers. Sixteen units would be restricted to households earning up to 60% of area median income for the full 75 years. The other 24 would be capped at 100% of AMI for the first 15 years, then up to 120% for the rest of the lease. That second tier is squarely aimed at working renters who earn too much for traditional subsidized housing but still struggle with Waikiki rents.
The developer is Centre Urban Real Estate Hawaii, which the city picked as its preferred negotiating partner in July 2025 after a Request for Qualifications that opened that February. The ground lease itself would be with an entity named Cardinal Ala Wai LLC. Spectrum News Hawaii described Centre Urban as a firm focused on urban infill and workforce housing, and reported that principal Martin Nguyen said the design would build on the site's 1940s-era walk-up history.
Hi.arch.y LLP is the architect on the project, based on the team the city pictured with the release. No general contractor has been named, and the release doesn't give a construction budget, financing sources or the lease payment.
The property has a long back story. The original apartment building went up in 1949 and sat vacant for roughly two decades, drawing trespassers and vandals, according to city officials. Honolulu took the land through condemnation, which the city says it completed in December 2023.
Demolition came next. The city pulled a building permit for the teardown in June 2025, and its demolition contractor, R.H.S. Lee, Inc., started clearing debris that month. Unitek Insulation handled remediation over several weeks before the structure itself came down in late summer. Crews staged equipment in the rear lot, reached through the neighboring Hawaiiana Gardens property.
After that, the development team met with the Waikiki Neighborhood Board in November 2025, and the city held a public hearing on the lease in July 2026. The hearing notice said units would be income-restricted at levels set by HUD, with none above 140% of AMI.
The developer's schedule is preliminary and depends on permits and approvals. It shows architectural design and a building permit application in the first quarter of 2027, construction starting in late 2027 and completion targeted for late 2028.
Cardinal at Ala Wai is one piece of a wider push by the city's Department of Housing and Land Management to put housing on public land. Its development portfolio lists other projects either underway or being lined up, including 42 units at Kihapai Place in Kailua, 127 rentals at Kaleimao Village in Ewa Beach and a planned 500 to 700 units at Iwilei Center.
Why it matters for Contractors
A 40-unit, six-story building on a tight infill lot isn't a mega-project, and that's the point for smaller Oahu trades. Jobs this size often lean on local subs for framing or concrete work, drywall, finish carpentry, MEP, elevators, waterproofing and site work, and the access constraints make experience with cramped urban lots worth something.
Nothing is out to bid yet, and no general contractor has been named. The realistic move right now is to watch for the full council vote on Resolution 26-237, then keep an eye on Centre Urban's team and the building permit filing expected in early 2027. That's when a GC is likely to start lining up subs ahead of a late-2027 start.
It's also worth tracking the city's broader public-land pipeline. Several sites on the housing department's list are still in pre-development, and each one that moves forward follows a similar path: developer selection, public hearing, council approval, then permits. Shops that know that sequence can get in front of the right people earlier.