Leland approves 20-year development agreement for Jackey's Creek, a 2,500-home project near Brunswick Forest

Leland council OKs a 20-year development agreement for Jackey's Creek near Brunswick Forest: about 1,600 homes, 900+ apartments, retail, offices and more.

Welcome sign for the Town of Leland, North Carolina. Photo: Idawriter / Wikimedia Commons, CC BY-SA 3.0

A huge planned community near Brunswick Forest cleared another hurdle Thursday night. The Leland Town Council voted 4-1 on Nov. 19 to approve a request tied to Jackey's Creek, a planned community of more than 1,200 acres near Brunswick Forest, over objections from residents worried about traffic, flooding and infrastructure (via WECT). Councilman Frank Pendleton cast the lone no vote.

The item was a development agreement under Article 10 of North Carolina's Chapter 160D, according to the town's public hearing notice. That's a contract between the town and the developer that locks in rules and commitments for a long buildout, not a new rezoning. The land, along US 17 and NC 133 northeast of Brunswick Forest and Mallory Creek, was annexed and zoned by the council in September 2025, WWAY reported at the time. It's currently zoned FCZ (FlexCode Zone) and PUD.

The developer is Atkinson Trail Developers, Inc., according to the town. As proposed, Jackey's Creek would include roughly 1,600 single-family homes, more than 900 multifamily units, more than 100,000 square feet of office space, more than 100,000 square feet of retail, a future elementary school and a full medical campus, WECT reported. The final draft agreement posted by the town lists the same housing and commercial program as what the developer "currently proposes," subject to change.

Supporters said the project would add about $5.56 million a year in sales and property tax revenue once it's complete, with buildout projected by fiscal year 2046-47.

Residents packed the chambers. "In other words, how do you solve issues associated with unprecedented growth by approving even more growth?" one neighbor asked, according to WECT. Councilmember Leland Hyer asked whether the agreement could be changed later; Town Manager David Hollis said an amendment could require legal review to make sure it stays valid, WECT reported.

The town's final draft of the agreement, the most recent version we could find, spells out what the developer is and isn't on the hook for:

The agreement runs 20 years, and the developer is asked to finish within that window, though it isn't obligated to build. It gets vested rights under the rules in place when the agreement is signed, and later town moratoria won't apply without its consent.

On roads, the developer would build a single-lane roundabout where Jackey's Crossing meets the project's main spine road, with right-of-way set aside to widen it to two lanes later. The spine road to NC 133 can be two lanes with a landscaped median. The developer must use "best efforts" to extend Jackey's Crossing north, while the town would use its best efforts to build a creek crossing, subject to funding and permits.

Water and sewer come through the town and H2GO, which jointly own the utility system, with service subject to availability. The developer would build the on-site lines and dedicate them after H2GO inspects and approves them. The draft also allows HDPE storm pipe and up to a handful of model homes in each section of the project.

The town manager would review the project every 12 months. We couldn't confirm whether the council approved the draft as written or with changes.

Why it matters for Contractors

A development agreement isn't a building permit, so nobody's breaking ground tomorrow. But it's the green light for up to two decades of work near Brunswick Forest: thousands of homes, apartments, shops and offices, plus the roads, storm drainage and utility lines to serve them.

The early work goes to site contractors. Clearing, grading, the roundabout and spine road, storm pipe and water and sewer lines that have to pass H2GO inspection all come first. If that's your trade, get to know Atkinson Trail Developers and the engineers it's using.

For small builders and trades, the play is the pods. The agreement allows model homes in each section, so watch the Town of Leland Planning department for subdivision plats and permits as each phase comes up. That's when homebuilders start hiring framers, roofers, electricians and finish crews, and on a 20-year project, getting in early can mean years of steady work.