Pulling a building permit in Lyme could soon cost nearly 50% more. The town's building official wants to raise fees that, by his account, haven't moved since at least 2001, and match them to the schedule next door in Old Lyme (via LymeLine).
Building Official Joshua Adams brought the idea to the Board of Selectpeople at its Nov. 16 meeting. The town's minutes confirm he presented a proposal to bring Lyme's rates in line with surrounding towns. Nothing has been adopted yet.
Here's how the two schedules compare. Lyme now charges $15 for the first $1,000 of project value and $10 for each $1,000 after that. Old Lyme's posted schedule, in effect since July 1, 2025, charges $30 for the first $1,000 and $15 for each additional $1,000.
Adams walked the board through a few examples, as LymeLine reported them:
A $50,000 project would go from about $520 to $765.
A $100,000 project would go from $1,020 to $1,515.
A $5 million project would go from $50,020 to $75,015, roughly $25,000 more right off the top.
His pitch is about who pays. Raising permit fees puts more of the building department's cost on the people pulling permits, not on every taxpayer in town. "It's not everyone paying," Adams told the board.
Lyme leans heavily on property taxes, which make up about 88% of projected revenue in the town's current budget, according to LymeLine. That 2026-27 budget counts on $110,000 from building permits at today's rates.
Last year the town issued 348 permits and took in $128,665. Adams estimated the new schedule would have brought in roughly $45,000 to $50,000 more. This year looks a little slower. He counted 237 permits so far and expects to finish near 316, about 9% below 2025.
He was upfront that these are estimates. Lyme still keeps permit records on paper, and its log doesn't capture each job's declared value, so he can't run exact numbers. One or two big projects could swing the totals a lot. He recommended the town start tracking valuations.
Why Old Lyme? Adams said the two towns see similar residential and remodeling activity. Old Lyme has more commercial work, but most of what gets permitted there is residential, much like in Lyme.
He also said the fee change isn't tied to the town's own building plans, though the extra money could help with future costs. Budget talks have included upgrades to the Hamburg and Hadlyme fire stations and public works facilities.
Under local ordinance, the selectpeople are the ones who set permit fees, LymeLine reported. First Selectwoman Christy Zelek said the board expects to take the issue up in December. The town calendar lists Board of Selectpeople meetings on Dec. 7 and Dec. 21 at Town Hall. No effective date has been set.
Why it matters for Contractors
If you work in Lyme, plan on higher permit costs soon, even though nothing is final. On a typical $50,000 to $100,000 remodel, the bump is roughly $250 to $500 per job. That won't sink a project, but it's worth building into bids you're writing now for work that might not pull permits until after the board acts. If your contracts pass permit fees to the owner at cost, a quick heads-up to clients avoids surprises.
For shops that work both sides of the Lyme-Old Lyme line, there's a small upside: one fee schedule to remember instead of two. Old Lyme's posted schedule also lists a separate state education fee of $0.26 per $1,000, so check the final Lyme schedule for add-ons like that once it's adopted.
If you want a say, the December selectpeople meetings are open to the public. And if Lyme follows Adams's advice to start recording project values, expect the declared valuation on your permit application to get a closer look.