Chesapeake's Planning Commission has recommended denying a rezoning that would put up to 296 homes on the old White's Nursery property in Deep Creek, even after the developer trimmed the plan and offered to hold off on building permits for years (via WTKR News 3).
The vote at the commission's Nov. 12 meeting was 7-1. It's a recommendation only. City Council makes the final call, and the city's 2026 processing calendar sends rezonings heard by planners on Nov. 12 to council on Dec. 15. No council agenda has been posted yet.
The project, Stockton Meadows, comes from Kotarides Developers. According to the city staff report, it covers about 75.2 acres at 3133, 3113 and 3041 Old Mill Road and 3225 Weiss Lane, and would rezone the land from R-15s and A-1 to conditional R-MF-1 multifamily. The plan calls for 100 detached single-family condos, 140 attached townhouse-style condos and 56 units in four-unit buildings, about 3.9 units per acre.
The unit count has moved around. A preliminary plan shown to neighbors in late 2025 had 259 units. The first formal submission came in at 359, and Kotarides cut it to 296 after staff asked for a plan closer to the comprehensive plan, which caps the area at about four units per acre.
Staff recommended approval with proffers. The big one is timing. Kotarides offered to hold building permits until the new elementary school at Culpepper Landing opens and the Deep Creek Bridge replacement is finished, or until Jan. 1, 2029, whichever comes first. The developer also offered about 6 acres for a public park, a 10-foot multi-use trail, and land for road widening and fixing a curve.
Those two pieces of infrastructure are the heart of the fight. Deep Creek Central Elementary is at 137.2% of capacity, against a city standard of 120%. Chesapeake Public Schools expects the new Culpepper Landing school to open in fall 2027, with new attendance zones easing Deep Creek Central and three other schools.
On traffic, the staff report estimates about 2,428 vehicle trips a day from the project. The George Washington Highway and Moses Grandy Trail intersection runs at level of service F at peak times, and the city expects it to improve to C once the bridge work is done. That project, led by the U.S. Army Corps of Engineers' Norfolk District with $20 million from the city, replaces the 1934 two-lane drawbridge carrying U.S. 17 over the Dismal Swamp Canal with a five-lane bascule bridge. The Corps expects to finish in 2028.
Neighbors weren't swayed. "We are the folks that will be affected by the rezoning," Deep Creek resident Donna Miller told the commission, according to WTKR. Residents raised traffic, crowded schools and strained infrastructure.
The land has been in the White family for nearly a century. The last crop was grown there in spring 2024.
Why it matters for Contractors
This one shows how much school capacity and road projects can weigh on a rezoning. Even with staff support and a permit hold that could push vertical work into 2028, planners said no. If you're a builder looking at land in fast-growing parts of Chesapeake, factor school capacity and road projects into your timeline before you sign.
For trades and small builders, there's no work here yet, and maybe not for a while. If council approves it Dec. 15, the permit hold means site work could come first and homes later, likely after the bridge opens. If council denies it, expect a revised plan down the road.
Either way, the Dec. 15 council meeting is the date to watch. The Deep Creek Bridge itself is the other one: it's the project this plan, and the area's traffic, are waiting on, with completion expected in 2028.