Drop-ceiling material is getting pricier again. CertainTeed Architectural told U.S. customers in an Oct. 23 letter that prices on its ceiling lines go up for shipments on or after Nov. 23, with grid and panels climbing as much as 10% (via ABC Supply Interiors).
Here's the breakdown. All grid products, accessories included, go up by as much as 10%. All panel products go up by as much as 10%. All specialty products, accessories included, go up by as much as 8%. The company points to ongoing inflation and higher costs for raw materials and freight.
The letter also says shipments "may be managed as necessary" to keep product availability consistent. That's polite language for possible allocation, so if you're counting on a big delivery right before the deadline, don't assume it'll show up in full.
Note the "up to" on every line. The letter sets a ceiling, not a flat rate, so what you actually pay depends on the product and your account. Your supplier should be able to tell you the real number on the items you buy most.
CertainTeed Architectural is the ceilings and walls business CertainTeed formed in 2020, combining its own lines with Hunter Douglas Ceiling & Wall Products, Norton Industries and Decoustics. Its lineup runs from mineral fiber and fiberglass panels to metal, wood and felt systems, plus standard grid and trim and the QuickSpan locking drywall grid. Specialty work like Decoustics acoustical systems and Metalinx expanded metal ceilings falls under that category.
CertainTeed isn't moving alone. Armstrong Ceiling Solutions put through its own increase on Aug. 3, raising mineral fiber panels 7%, fiberglass panels 9% and suspension systems, trims and accessories included, 10%. Armstrong blamed volatile energy costs and higher prices for inputs including steel, aluminum, paint and fiberglass.
Steel framing has been on the same track. Kamco Supply's announcements page shows a string of increases from ClarkDietrich, CEMCO, Marino\WARE and Super Stud running from August through October, including 10% from Marino\WARE on Sept. 1 and 15% from Super Stud on Sept. 8.
Why it matters for Contractors
If you do tenant improvements, office refreshes or medical and school suites, this one is aimed right at your bids. Because the new pricing is tied to the ship date, not the order date, placing a PO before Nov. 23 won't protect you unless the material actually ships before then. Ask your supplier what can go out ahead of the change.
For anything quoted with CertainTeed grid or tile that won't ship until later, rebuild the material number with the full 10% unless your supplier gives you something firmer. And on longer jobs, an escalation clause on ceiling and framing material is worth the awkward conversation, since grid, studs and panels have all moved this year.