CEMCO, the California steel framing and metal lath maker, is raising prices again. A customer letter dated Oct. 23 says prices on all of its steel-based products, in every market, go up on shipments made on or after Monday, Nov. 30 (via ABC Supply).
The company calls it the 12th increase it has announced in 2026, which it describes as unprecedented in its 52-year history. That lines up with the company's founding in 1974, per its supplier listing with the Steel Framing Industry Association's buildsteel.org site.
As with its earlier letters, CEMCO doesn't give a percentage. Updated price sheets are supposed to come from sales reps the week of Nov. 23, a week before the new prices kick in.
The letter, signed by the CEMCO Sales Management Team, points to the same pressures it has cited all year. It says domestic mills are running behind because supply is tight with fewer imports coming in, and that mills keep raising their prices month over month. It adds that higher freight costs in both directions, plus rising prices for packaging, parts and other supplies, are squeezing its costs. CEMCO also says the run-up is hitting both forward pricing and committed jobs that were quoted before steel spiked.
This is the second CEMCO move this month. A separate adjustment effective Nov. 2 was already on the books.
Earlier letters posted by dealers show how the year has gone. A March 4 letter for an April 6 increase called it the fourth consecutive one and pointed to steel imports falling every month since a peak the previous July, which CEMCO tied to the doubling of Section 232 steel tariffs. An April 30 letter for June 1 said it was the sixth increase in six months, citing tight inventories, longer mill lead times and higher galvanized sheet costs. A May 29 letter for June 29 added coating upcharges of 10 percent to move from G40 to G60 or from G60 to G90, and 20 percent to go from G40 to G90, blaming high zinc prices.
Federal data backs up the trend. The Bureau of Labor Statistics producer price index for steel mill products, published through the St. Louis Fed's FRED database, stood at 388.6 in September 2026. That's about 28 percent higher than a year earlier and roughly 23 percent above January 2026.
CEMCO makes steel studs and track, metal lath and fire-rated products and lists plants in City of Industry and Pittsburg, Calif., Denver and Fort Worth, Texas. Its products are sold through distributors, so the increase reaches contractors through their supply house rather than directly.
Why it matters for Contractors
If you frame with steel or hang lath for stucco, especially in the West and Texas, assume your material cost goes up again Dec. 1 and price jobs accordingly. Anything you can buy and take delivery on before Nov. 30 avoids this round, so it's worth calling your supplier now about open orders.
Earlier CEMCO letters honored job quotes committed in writing within 30 days and held quoted pricing for 180 days. The Nov. 30 letter doesn't repeat that language, so ask your rep whether it still applies and get any job quote locked in writing.
For small shops, the bigger lesson is in the count. Twelve increases in a year means a bid that's a month old may already be wrong. Short quote validity windows and a material escalation clause in your contracts aren't optional this year.