Summit County makes traffic studies mandatory for bigger developments

Summit County now requires transportation impact studies for projects adding 25+ peak-hour trips. What builders should expect on cost, scope and timing.

Kimball Junction in Summit County, Utah. Photo: Patrick Hendry via Unsplash and Wikimedia Commons, CC0

Developers in Summit County can no longer wave off a request for a traffic study. The Summit County Council on Nov. 4 approved rules that require a transportation impact study for any project expected to add at least 25 vehicle trips during a peak hour (via KPCW).

County staff have been asking for these studies on projects that size for years. The problem was that nothing in the code made it stick. "If a developer were to say, 'I just don't want to do it,' we don't have any teeth in our code to make them do it," Principal Planner Ray Milliner told the Snyderville Basin Planning Commission in August, according to TownLift.

The council passed two ordinances, numbered 1024 and 1025, after separate public hearings, TownLift reported. One adds a traffic impact study subsection to Section 10-4-10 of the Snyderville Basin Development Code. The other creates a new Section 11-2-7 in the Eastern Summit County Development Code, according to the county's public meeting notices. Both planning commissions reviewed the changes earlier this year and sent them to the council. TownLift reported the rules take effect 13 days after publication.

Eva De Laurentiis, the county's transportation planning deputy director, told the council the county uses the studies "as a tool to make recommendations and require modifications" to development proposals, KPCW reported. A study looks at existing traffic, the trips a project is expected to generate, how nearby intersections will hold up, road capacity, new driveways and safety concerns.

What comes out of a study can cost real money. Depending on the findings, the county can ask for turn lanes, traffic signals, roundabouts, restriping, sidewalks, trails or bike and pedestrian improvements, and applicants generally pay for or build them. TownLift's September coverage pointed to two recent examples: the new Maverik near Quinn's Junction, which got a signal and turn lane coordinated with UDOT, and the Whole Foods project at Canyon Corners, which added turn lanes, internal circulation changes and a bus pullout.

The study itself isn't cheap either. De Laurentiis estimated $20,000 to $40,000 per study when the planning commission took up the proposal, TownLift reported. The draft called for the work to be done by an engineer licensed in Utah, and the county uses Institute of Transportation Engineers trip-generation data to estimate how many trips a project will produce. Studies can cover individual phases and peak winter conditions, not just final buildout.

How big a project has to be to hit the trigger depends on the use. The county's 2023 transportation impact fee analysis counts a single-family home as roughly one evening peak-hour trip, so a subdivision of about two dozen houses lands near the line. A busy commercial use gets there much faster. De Laurentiis said it'll mostly be the largest new developments that need one.

The Snyderville Basin commission had recommended defining the peak periods as 7 to 10 a.m. and 3 to 6 p.m., wider than staff's original two-hour windows, to account for school traffic, ski-area openings and afternoon congestion. Staff said the requirement isn't retroactive for complete applications already submitted, and they plan to publish a checklist spelling out what a study must contain.

The studies are separate from the transportation impact fees the county already charges. Those fees were expanded countywide in 2023 under Ordinance 958 and run about $3,427 per single-family home, about $1,939 per low-rise apartment unit and about $38,494 per 1,000 square feet of daycare space, according to the county's fee analysis. The county collects roughly $1 million a year from them, which has gone to projects like Old Highway 40, Old Ranch Road and planned roundabouts in Silver Summit, TownLift reported.

Why it matters for Contractors

For most small shops, this won't change much day to day. A remodel, an addition or a handful of spec homes won't come close to 25 peak-hour trips. Where it does matter is on the larger subdivisions, multifamily projects and commercial jobs in the Snyderville Basin and eastern Summit County, because a study adds time and cost up front and can add road work to the scope.

If you're a builder or developer putting together a bigger project under the county's development codes, budget for the study and for whatever it might require, and ask planning staff early whether your project trips the threshold. For site, paving and concrete contractors, the upside is that required turn lanes, sidewalks and intersection fixes are work somebody has to build. Watch for the county's checklist, which should make the requirements easier to plan around.