ClarkDietrich, one of the big names behind the steel studs and track on commercial jobs, is raising prices twice more before winter is out. In a Nov. 2 letter to customers, the West Chester, Ohio, company said two consecutive nationwide increases will take effect Dec. 1, 2026, and Jan. 4, 2027 (via ClarkDietrich, shared by distributor KAM).
The company pins the moves on domestic steel mills, saying the increases respond to continued mill price increases and surcharges being passed along in the coming months.
The letter doesn't say how big either increase is. There's no percentage and no dollar figure. ClarkDietrich says updated price lists will be published to all markets before each effective date, so the real numbers will come through your supplier.
It also doesn't list specific products. Distributor Negwer, which posted the notice on its own site, describes the two increases as applying to all products (via Negwer). An earlier ClarkDietrich letter this year, for an Aug. 3 increase, spelled it out as all products nationwide, both exterior and interior lines.
Two lines in the Nov. 2 letter matter most for anyone with work on the books:
Pricing is set when the material ships. ClarkDietrich reminds customers that invoice pricing is determined at the time of shipment.
Existing quotes will be honored, but only under the company's job quote policy.
That second point is where small contractors can get caught. ClarkDietrich's posted job quote policy, dated Feb. 28, 2022, sets a standard quote duration of 180 days for quotes over 40,000 pounds. Quotes have to be awarded within 30 days to stay valid, and they're activated only through the company's CD Link customer portal. The policy says emails, verbal or written commitments don't count as activating a quote (ClarkDietrich quote policy).
The policy also allows escalators based on market conditions, and offers a price protection option for longer jobs, up to 24 months from the quote date, that has to be set up within 60 days and adds a percentage to the price.
In practice, most small shops buy through a distributor rather than holding quotes directly, so the distributor is usually the one managing activation. It's still worth asking whether the material on your bids is tied to an activated quote.
ClarkDietrich has been raising prices steadily. Distributor Kamco Supply's news page lists ClarkDietrich increases effective Aug. 3, Sept. 1 and Oct. 1 of this year (Kamco Supply news). Add Dec. 1 and Jan. 4, and that's five increases in roughly six months.
ClarkDietrich isn't alone. Marino\WARE told customers Nov. 3 it will raise prices at least 10% on all steel products for deliveries on or after Jan. 4, on top of increases it already announced for November and December (via Marino\WARE). So two major cold-formed steel framing suppliers have increases landing the same week in January.
Why it matters for Contractors
If you frame interiors, hang board or do commercial tenant improvements, steel framing prices are now moving faster than a typical bid cycle. A job you priced this fall could be bought at two price levels higher than you planned.
A few things worth doing now:
Call your supplier and ask which manufacturer's studs and track are on your open quotes, when ClarkDietrich's new price lists will be out, and whether your material is covered by an activated quote.
Look at delivery timing. Because pricing is locked at shipment, taking delivery before Dec. 1 or before Jan. 4 can keep a job at today's price, if your site and schedule can handle the material.
Put a material escalation clause or a short price-hold window in new proposals, especially for work that won't frame until spring.
And if your customer is weighing whether to sign now or later, it's fair to tell them plainly: steel framing has gone up repeatedly this year, and two more increases are already scheduled.