Titan Development has broken ground on Quinto Sol, a roughly 160-acre community on Albuquerque's Southwest Mesa where D.R. Horton plans to build more than 280 single-family homes in the first phase (via KRQE).
Crews are now doing site work on Phase One near Unser Boulevard and Blake Road. Titan expects to finish that work by late 2027, KRQE reported, after which D.R. Horton will start building houses, with the first residents likely moving in early 2028.
The name honors the late New Mexico author Rudolfo Anaya, whose novel "Bless Me, Ultima" won the Premio Quinto Sol, a prize for Chicano literature, in the early 1970s. A nearby elementary school already carries his name, and Titan plans street names inside the community that tie back to him. "We're really just trying to pay homage to him," Titan partner Brian Patterson told KRQE.
City records fill in the details behind the groundbreaking. The project shows up in Albuquerque's planning files as "TA Lands," filed by TA Land Company, an entity at Titan's office address.
In October 2025, the city's Development Hearing Officer approved a bulk land plat splitting about 158.5 acres between Unser and 98th Street SW into four tracts, with about 11 acres dedicated as city right-of-way. In February 2026, the hearing officer approved, with conditions, a major preliminary plat for Phase 1: 283 lots on about 55 acres, zoned MX-T and R-1A. That approval came with waivers for block length, street curves and 35 lots backing onto Unser.
There are hurdles left. The site has mapped floodplain, so the regional flood control authority, AMAFCA, conditioned plat signature on FEMA approving a conditional map revision. The city also required a recorded infrastructure improvements agreement before a final plat, and set a one-year window for that final plat. The city approved a temporary deferral that lets lot sidewalks go in one by one as homes are finished.
Earlier sketch plans from the project engineer, Bohannan Huston, put full buildout at about 885 single-family lots on roughly 125 acres, built in phases. Phase 1 would get Albuquerque Bernalillo County Water Utility Authority water looped to an existing 12-inch line in Unser, and sewer would drain east to an existing 27-inch line.
In 2024, the city's Environmental Planning Commission recommended zone changes on about 73 acres of the property to MX-T and R-1A. The commission found infrastructure capacity adequate, and only one neighbor called with questions.
Why it matters for Contractors
For dirt, utility and concrete contractors, Quinto Sol's site work is underway now and runs through 2027: grading, drainage ponds, water and sewer mains, curb and gutter for 283 lots.
For trades who work new homes on the West Side, the bigger number is behind it. If later phases follow the sketch plans, this could be a multiyear pipeline of D.R. Horton starts on the Southwest Mesa. Production builders typically line up trade partners early, so if you want framing, HVAC, plumbing, electrical or flatwork on these homes, the time to get on D.R. Horton's Albuquerque vendor list is before vertical construction starts in 2028.
Watch the FEMA map revision and the final plat. Those are the two approvals that decide whether home construction starts on schedule.