New Hampshire builders say Build America, Buy America rules are slowing affordable housing

New Hampshire builders say federal Build America, Buy America rules and slow HUD waivers are delaying affordable housing. What it means for contractors.

The New Hampshire State House in Concord. Photo: Quintin Soloviev via Wikimedia Commons, CC BY 4.0

Affordable housing developers in New Hampshire say a federal made-in-America rule is pushing their projects behind schedule and over budget, and they want Washington to loosen it, or at least speed it up (via Monadnock Ledger-Transcript). The story, reported by Jackie Harris of NHPR and shared through the Granite State News Collaborative, collects complaints from builders, a housing nonprofit and a member of Congress.

The rule is Build America, Buy America, usually shortened to BABA. It came in with the 2021 Infrastructure Investment and Jobs Act and requires iron and steel, construction materials and manufactured products used in federally funded infrastructure to be produced in the U.S., according to HUD's BABA page. When HUD money is in an affordable housing deal, that requirement comes along with it.

The sharpest line came from John Egan of Avesta Housing, a nonprofit that works in Maine and New Hampshire. Speaking at an October meeting of the Mount Washington Valley Coalition, he called it "a new plague on affordable housing development." According to NHPR, an Avesta project of 40 apartments, most rented below market rate, is behind schedule and $2 million over budget after trying to buy the required materials from U.S. producers. The reports don't say where that project is.

The rule does allow exemptions. HUD lists three kinds of waivers: public interest; nonavailability, for products not made here in enough quantity or acceptable quality; and unreasonable cost, when going domestic would raise the overall project cost by more than 25%. The complaint is timing. Developers told NHPR waivers can take more than a year to come through.

Other New Hampshire examples in the reporting:

In Tilton, a 20-room expansion of the New Hampshire Veterans Home has been waiting on a waiver. Rep. Maggie Goodlander's office said the project couldn't find U.S.-made heavy-duty grab bars or certain heating and sprinkler parts, and some items assembled here still didn't qualify because too many of their components were imported. The state's congressional delegation asked the VA in September to hurry it along. As of NHPR's report, it was still pending.

In New Hampton, developer Kevin Lacasse said an infrastructure job at a manufacturing park a few years ago ran over budget and late because valves for the water system weren't readily available from domestic makers. He argued the public would be better off if projects could "source their materials from the cheapest qualified place possible."

Matt Mayberry, CEO of the New Hampshire Home Builders Association, put it more bluntly in a release quoted by NHPR: "Release the bureaucratic shackles and let us do our jobs." Back in June, when the bill described below was introduced, he said in Goodlander's announcement that his members report BABA "is inadvertently adding hundreds of thousands of dollars to construction costs."

On the policy side, Goodlander, a New Hampshire Democrat, and Rep. Mike Flood, a Nebraska Republican, sent HUD a letter last week urging faster waivers and an exemption process for products in short supply from U.S. manufacturers. The two had already filed the Build Housing Affordably Act in June. According to Goodlander's office, it would have HUD study how BABA affects housing production, pause the expanded rules for housing programs during that study, and set up a more predictable waiver process. It wouldn't repeal BABA.

New Hampshire isn't alone. An Associated Press report carried by WCAX in March found developers across the country waiting six months or more on many HUD waivers, some paying consultants tens of thousands of dollars to track down American-made materials. Supporters of the rule, including the United Steelworkers, argued in that report that cost complaints are overblown.

Why it matters for Contractors

If you sub or GC on affordable housing in New Hampshire, the first question is whether federal money is in the deal. If it is, BABA can reach things you normally just order: fixtures, HVAC, valves, sprinkler parts, even grab bars. Expect owners to ask for country-of-origin paperwork, and don't assume a product counts because it's assembled here.

Price and schedule accordingly. Ask early which materials already have waivers, check HUD's waiver list, and build lead time and contingency into bids so a slow waiver doesn't come out of your margin. HUD also lists a small-grant waiver for projects at or under $350,000 and a de minimis allowance of up to 5% of covered material costs, capped at $1 million, so ask the owner which of those apply. If nobody on the project can answer, that's a risk worth pricing in.