State and local leaders cut the ribbon Nov. 13 on The Dakota, a 114-unit affordable apartment building on Blackstone Avenue in central Fresno where the old Smuggler's Restaurant used to sit (via California Strategic Growth Council). The council says construction should wrap up next month.
The four-story building sits on 1.83 acres at the southwest corner of Blackstone and Dakota avenues, at 3787 N. Blackstone. It's being developed by UPholdings and RH Community Builders, the same pair that turned the neighboring Smuggler's Inn hotel into Crossroads Village. City records list the owner as Dakota Fresno, LP, the general contractor as Quiring General LLC and the architect as Paul Halajian Architects.
The units are for households earning 30% to 60% of area median income, and 45 of them are set aside for veterans. City documents show 54 one-bedroom, 30 two-bedroom and 30 three-bedroom apartments, with rents from $495 to $1,371 when the HOME loan was approved in 2025.
The money is a big stack. The state put in about $53 million through its Affordable Housing and Sustainable Communities program (AHSC), the Infill Infrastructure Grant program and HOME funds. City records put the total development cost at about $70.3 million, with tax credit equity and a construction and permanent loan from KeyBank's community development lending arm filling out the rest. The project broke ground in April 2025.
"The Dakota development will help fill a critical gap in affordable housing in Fresno," said Samuel Assefa, who chairs the Strategic Growth Council and directs the Governor's Office of Land Use and Climate Innovation.
The building is designed for Fresno heat. The release lists air conditioning, tree and balcony shading, better insulation and air filtration. Earlier coverage in The Business Journal described it as a zero net energy design that wraps around a 50-year-old cork oak. Inside, there's a fitness room, community room and kitchen, a playground and bike parking, plus a free on-site clinic run by Family Healthcare Network.
The part contractors may want to watch is outside the building. AHSC money also pays for transportation work along the corridor: about a lane mile of protected bikeways, three new crosswalks, nearly 5,000 feet of new or improved sidewalk, bus stop upgrades and more frequent service on FAX Route 39. Under a 2024 city council item, the City of Fresno accepted about $15.6 million of the award for that work, including roughly $3.6 million for Public Works to build Class IV bike lanes on both sides of Blackstone, a 12-foot sidewalk between Shields and Dakota, new west-side sidewalk from Shields to Dayton, ADA curb ramps and a pedestrian signal at Dakota and Garland.
Those street improvements have to be finished by 2028, according to the city. A separate South Blackstone mobility plan pegged the Shields-to-Dakota segment at about $5 million. We couldn't find a construction contract awarded yet for that stretch.
One timing note: city loan documents gave an estimated completion date of May 30, 2027, while the state now says December. Either way, the building is close, and the corridor work is the next phase.
Why it matters for Contractors
The building is nearly done, so the general contractor's sub list is mostly set. The opportunity is the street work. Fresno Public Works still has bike lanes, sidewalks, curb ramps and a pedestrian signal to build on Blackstone between Shields and Dakota before a 2028 deadline, and in 2024 the city said it still needed local Measure C and Measure P money to fully fund it.
If you're a concrete, flatwork, striping or electrical shop in the Valley, keep an eye on the city's bid postings for the South Blackstone segments. Recent Blackstone and trail contracts have gone to regional firms in the $4 million to $5 million range, which is within reach for mid-size subs teaming on a bid.
Projects like this one also tell you where state money is flowing: AHSC pairs housing with transit and street work, so each award tends to bring a public works job with it.