The cleanup money is in for the old Dentsply headquarters on York's West College Avenue. Pennsylvania has approved a $1 million Industrial Sites Reuse Program grant to the Redevelopment Authority of the City of York to pay for soil testing, asbestos abatement and pulling underground storage tanks off the 17.3-acre property at 470-600 W. College Ave. (via Pennsylvania DCED).
The grant was announced Nov. 23 by state Community and Economic Development Secretary Rick Siger and Environmental Protection Secretary Jessica Shirley. It's the environmental piece of a much bigger plan to turn the dental manufacturer's longtime campus into a mixed-use neighborhood.
According to the state, the finished site could hold up to 178 housing units, including 12 affordable townhomes, along with office space for both businesses and nonprofits. The plan also calls for a job training center that the state says could run apprenticeship programs in in-demand trades for roughly 100 or more people a year.
"Removing hazards like asbestos and repurposing industrial sites into usable housing is a win-win," Shirley said in the announcement.
The Industrial Sites Reuse Program covers environmental assessment and remediation on former industrial land, and it's limited to applicants that didn't cause the contamination. That fits here: the redevelopment authority bought the campus from Dentsply Sirona at the end of 2023.
The city's announcement of that purchase, made in January 2024, lays out what's on the ground. The property covers 28 parcels and nine buildings with close to 300,000 square feet of old office, manufacturing and lab space. It sits where West College Avenue meets Grantley Road, between York College and Codorus Creek, and the West College Avenue plant dates back to 1907. The authority said it bought the site to keep it from sitting empty and going downhill while it was on the market.
At the same time, the city named its developer: York Realty Partners, a partnership between Knight Street Capital, a Providence, Rhode Island, adaptive reuse firm, and CAM Construction Co., a Baltimore general contractor founded in 1962. The city said the developer would rehab the existing buildings, and that parcels would be handed over to it in stages over several years as work moves along. The two firms have partnered on redevelopments in Warwick, Rhode Island, and Baltimore and on the Stehli Silk Mill project in Lancaster.
This isn't the site's first state check. In May, Gov. Josh Shapiro's office awarded the redevelopment authority $1,583,562 from the new Mixed-Use Housing Development Pilot Program for the vacant Dentsply complex. That release described a first phase with 81 apartments plus retail, office and makerspace.
The project has also been a test case for the state's faster permitting push. Shirley said the Dentsply site was the first to use a permit under DEP's SPEED program, short for Streamlining Permits for Economic Expansion and Development. When DEP announced its first SPEED permit in November 2025, it described a stormwater permit change for the Towns at York Creek, a York mixed-use development with townhomes, apartments and storefronts, approved in 51 days including the required 30-day public comment period.
Neither the state nor the city has posted a construction schedule for the housing.
Why it matters for Contractors
The work that's funded right now is specialty work: environmental assessment, asbestos abatement and underground tank removal. Licensed abatement firms and tank removal contractors in York County should keep an eye on the redevelopment authority for any procurement tied to this grant, though the state didn't say how that work will be contracted.
For everyone else, this is a long-runway job. CAM Construction is the general contractor partner on the development team, and adaptive reuse of nine old industrial buildings, plus new townhomes, usually means years of interior, mechanical and finish packages. Small subs who want a piece should get on the developer's radar early and watch York City Planning Commission agendas for land development filings on the West College Avenue parcels.
The training center is worth watching too. If it opens with trades apprenticeships as planned, it could become a local hiring pipeline for small shops that can't afford to run their own programs.